List of steps
(Total number of steps: 58)
Meet Investment Promotion Centre (IPC)
Obtain investment intent  (4)
Prepare master plan drawing profile  (1)
Obtain land location  (11)
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of documents  (2)
Obtain certified translation of documents  (2)
Obtain approval of master plan  (2)
Obtain approval of environment impact assessment (EIA) report  (6)
Obtain authenticated copies of documents  (1)
Declare investment project information online
Obtain investment registration certificate (IRC)  (2)
Obtain authenticated copies of IRC  (1)
Obtain Enterprise Registration Certificate (ERC)  (3)
Make seal and notify seal specimen  (2)
38
Make seal
Open bank account  (1)
Obtain approval of land lease and sign land lease contract  (3)
Obtain authenticated copies of documents  (1)
Obtain land use right certificate  (2)
Obtain certificate of fire prevention and fighting approval  (3)
Obtain authenticated copies of documents  (1)
Obtain approval of the conceptual plans of project  (3)
Obtain investigation on construction design  (3)
Obtain construction permit  (2)

Preview & Print

Properties
 
58
Collect construction permit
(last modified: 8/21/2017)

Contact details

Entity in charge

Danang Department of Construction

Floor 12th, Danang Administration Centre building, No. 24 Tran Phu street , Danang
Tel: +84 511 356 5566
Website: http://www.sxd.danang.gov.vn/en/web/english

Unit in charge

Counter 6/ 7 - Reception and release division - Ground floor - Danang Administration Centre

Mon: 07:30-11:30, 13:30-17:30
Tue: 07:30-11:30, 13:30-17:30
Wed: 07:30-11:30, 13:30-17:30
Thu: 07:30-11:30, 13:30-17:30
Fri: 07:30-11:30, 13:30-17:30

Person in charge

Mrs. Pham Thi Le Dung

Tel: +84 511 3561 817

Expected results

Construction permit 01 - Construction permit
Payment receipt 01 - Payment receipt

Requirements

1. 01 - Libre deuda de patente
Receipt of construction permit application (original)
2. 01 - Libre deuda de patente
Passport or Vietnamese ID card of investor (original)
For case of authorization
1. 01 - Libre deuda de patente
Passport or Vietnamese ID card of authorized person (original)
2. 01 - Libre deuda de patente
Power of attorney (original)
issued by investor for his/her legal representative in case investor is unable to come to collect the result

Costs

Cost detail

Hypothesis

VND 100,000
Construction permit fee
Payment methods: cash

Time frame

Waiting time in queue: Max. 5mn
Attention at counter: Max. 10mn

Legal justification

1. Circular 03/2001/TT-BTC of Ministry of Finance, guiding the regime of collection, management of construction licence fee
Circular 03/2001/TT-BTC of Ministry of Finance, guiding the regime of collection, management of construction licence fee
Article I.3

Additional information

After having the construction license, investor can start the construction work

Recourse: Danang Department of Construction

Entity in charge

Danang Department of Construction

Floor 12th, Danang Administration Centre building, No. 24 Tran Phu street , Danang
Tel: +84 511 356 5566
Website: http://www.sxd.danang.gov.vn/en/web/english

Unit in charge

Counter 6/ 7 - Reception and release division - Ground floor - Danang Administration Centre

Mon: 07:30-11:30, 13:30-17:30
Tue: 07:30-11:30, 13:30-17:30
Wed: 07:30-11:30, 13:30-17:30
Thu: 07:30-11:30, 13:30-17:30
Fri: 07:30-11:30, 13:30-17:30

Person in charge

Mrs Le Hong Thu

Chief of the Office
Tel: +84 511 3822 134