Meet Investment Promotion Centre (IPC)
Obtain investment intent  (4)
Prepare master plan drawing profile  (1)
Obtain land location  (11)
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of documents  (2)
Obtain certified translation of documents  (2)
Obtain approval of master plan  (2)
Obtain approval of environment impact assessment (EIA) report  (6)
Obtain authenticated copies of documents  (1)
Declare investment project information online
Obtain investment registration certificate (IRC)  (2)
Obtain authenticated copies of IRC  (1)
Obtain Enterprise Registration Certificate (ERC)  (3)
Make seal and notify seal specimen  (2)
38
Make seal
Open bank account  (1)
Obtain approval of land lease and sign land lease contract  (3)
Obtain authenticated copies of documents  (1)
Obtain land use right certificate  (2)
Obtain certificate of fire prevention and fighting approval  (3)
Obtain authenticated copies of documents  (1)
Obtain approval of the conceptual plans of project  (3)
Obtain investigation on construction design  (3)
Obtain construction permit  (2)

Preview & Print

Properties
 
25
Prepare EIA report
(last modified: 8/21/2017)

Costs

( ver detalles )

Timeframe ( ver detalles )

Espera hasta paso siguiente

VND 20000000
0 mn  -  0 mn
30 days  -  45 days

Expected results

EIA report x7 01 - EIA report

Requirements

1. Investment project
Investment project (Simple copy)

Costs

Cost detail

Hypothesis

VND 20,000,000
EIA report making fee for referrence only
Payment methods: cash, bank transfer
This is package service contract therefore the cost will be determined based on project scale and complexity.

Time frame

The EIA report will take about 30 days to be completed and another 30 days counting from the date of submission of application file to the date of attending meeting with Appraisal council.
Attention at counter: Min. 10mn - Max. 30mn
Waiting time until next step: Min. 30 days - Max. 45 days

Legal justification

1. Law  No. 52/2005/QH11 of National Assembly on Environmental Protection
Law No. 52/2005/QH11 of National Assembly on Environmental Protection
articles 18, 19, 20
2. Decree 80/2006/ND-CP of the Government detailing and guiding the implementation of a number of articles of the Law on environmental Protection
Decree 80/2006/ND-CP of the Government detailing and guiding the implementation of a number of articles of the Law on environmental Protection
articles 8, 9
3. Decree 29/2011/NĐ-CP of the Government providing strategic environmental assessment, environmental impact assessment and environmental protection commitment (Eng)
Decree 29/2011/NĐ-CP of the Government providing strategic environmental assessment, environmental impact assessment and environmental protection commitment (Eng)
articles 12, 13, 14, 15, 16, 17
4. Circular 26/2011/TT-BTNMT of Ministry of Natural Resource and Environment specifying some articles of Decree 29/2011/ND-CP on strategic environment assessments, environment impact assessments, environment protection plans
Circular 26/2011/TT-BTNMT of Ministry of Natural Resource and Environment specifying some articles of Decree 29/2011/ND-CP on strategic environment assessments, environment impact assessments, environment protection plans
articles 10, 12
5. Decision 23/2010/QĐ-UBND of Danang People's Committee regulating environmental protection in Danang (Viet)
Decision 23/2010/QĐ-UBND of Danang People's Committee regulating environmental protection in Danang (Viet)
Article 4

Additional information

* Projects subject to make EIA report are listed in Appendix II to Decree 21/2008/ND-CP (see the above attached list). EIA report must be appraised and approved by provincial people’s committee, except projects that are appraised and approved by the Ministry of Natural Resources and Environment as listed in Appendix III to Decree 29/2011/ND-CP. For other projects, the company needs to make and register the written environment protection commitment to the district-level people’s Committee where the project is located.
* A company being the owner of an investment project for which an environmental impact assessment (EIA) report must be formulated shall carry out itself, or hire a consultancy organization which satisfies all conditions stipulated in Article 8 of Decree 29/2011/ND-CP to make EIA report for the project.
* This is package service contract therefore the cost will be determined based on project scale and complexity.
Certification of EPA Certification of EPA
List of projects requiring EIA report List of projects requiring EIA report
Powered by eRegulations (c), a content management system developed by UNCTAD's Investment and Enterprise Division, Business Facilitation Program and licensed under Creative Commons License