The EIA report will take about 30 days to be completed and another 30 days counting from the date of submission of application file to the date of attending meeting with Appraisal council.
Attention at counter:
Min. 10mn - Max. 30mn
Waiting time until next step:
Min. 30 days - Max. 45 days
Law No. 52/2005/QH11 of National Assembly on Environmental Protection
articles 18, 19, 20
2.
Decree 80/2006/ND-CP of the Government detailing and guiding the implementation of a number of articles of the Law on environmental Protection
articles 8, 9
3.
Decree 29/2011/NĐ-CP of the Government providing strategic environmental assessment, environmental impact assessment and environmental protection commitment (Eng)
articles 12, 13, 14, 15, 16, 17
4.
Circular 26/2011/TT-BTNMT of Ministry of Natural Resource and Environment specifying some articles of Decree 29/2011/ND-CP on strategic environment assessments, environment impact assessments, environment protection plans
articles 10, 12
5.
Decision 23/2010/QĐ-UBND of Danang People's Committee regulating environmental protection in Danang (Viet)
Article 4
* Projects subject to make EIA report are listed in Appendix II to Decree 21/2008/ND-CP (see the above attached list). EIA report must be appraised and approved by provincial people’s committee, except projects that are appraised and approved by the Ministry of Natural Resources and Environment as listed in Appendix III to Decree 29/2011/ND-CP. For other projects, the company needs to make and register the written environment protection commitment to the district-level people’s Committee where the project is located.
* A company being the owner of an investment project for which an environmental impact assessment (EIA) report must be formulated shall carry out itself, or hire a consultancy organization which satisfies all conditions stipulated in Article 8 of Decree 29/2011/ND-CP to make EIA report for the project.
* This is package service contract therefore the cost will be determined based on project scale and complexity.