Meet Investment Promotion Centre (IPC)
Obtain investment intent  (4)
Prepare master plan drawing profile  (1)
Obtain land location  (11)
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of documents  (2)
Obtain certified translation of documents  (2)
Obtain approval of master plan  (2)
Obtain approval of environment impact assessment (EIA) report  (6)
Obtain authenticated copies of documents  (1)
Declare investment project information online
Obtain investment registration certificate (IRC)  (2)
Obtain authenticated copies of IRC  (1)
Obtain Enterprise Registration Certificate (ERC)  (3)
Make seal and notify seal specimen  (2)
38
Make seal
Open bank account  (1)
Obtain approval of land lease and sign land lease contract  (3)
Obtain authenticated copies of documents  (1)
Obtain land use right certificate  (2)
Obtain certificate of fire prevention and fighting approval  (3)
Obtain authenticated copies of documents  (1)
Obtain approval of the conceptual plans of project  (3)
Obtain investigation on construction design  (3)
Obtain construction permit  (2)

Preview & Print

Properties
 
53
Collect opinion on the conceptual plans of project
(last modified: 8/21/2017)

Contact details

Entity in charge

Danang Department of Construction

Floor 12th, Danang Administration Centre building, No. 24 Tran Phu street , Danang
Tel: +84 511 356 5566
Website: http://www.sxd.danang.gov.vn/en/web/english

Unit in charge

Counter 6/ 7 - Reception and release division - Ground floor - Danang Administration Centre

Mon: 07:30-11:30, 13:30-17:30
Tue: 07:30-11:30, 13:30-17:30
Wed: 07:30-11:30, 13:30-17:30
Thu: 07:30-11:30, 13:30-17:30
Fri: 07:30-11:30, 13:30-17:30

Person in charge

Mrs. Pham Thi Luong / Mr. Le Van Hieu

Officer
Tel: +84 511 3561 817

Expected results

Approval of the conceptual plans 01 - Approval of the conceptual plans
Endorsed drawing of conceptual design 01 - Endorsed drawing of conceptual design

Requirements

1. 01 - Libre deuda de patente
Receipt of application file (original)

Time frame

Waiting time in queue: Max. 5mn
Attention at counter: Max. 10mn

Recourse: Danang Department of Construction

Entity in charge

Danang Department of Construction

Floor 12th, Danang Administration Centre building, No. 24 Tran Phu street , Danang
Tel: +84 511 356 5566
Website: http://www.sxd.danang.gov.vn/en/web/english

Unit in charge

Counter 6/ 7 - Reception and release division - Ground floor - Danang Administration Centre

Mon: 07:30-11:30, 13:30-17:30
Tue: 07:30-11:30, 13:30-17:30
Wed: 07:30-11:30, 13:30-17:30
Thu: 07:30-11:30, 13:30-17:30
Fri: 07:30-11:30, 13:30-17:30

Person in charge

Mrs Le Hong Thu

Chief of the Office
Tel: +84 511 3822 134
Powered by eRegulations (c), a content management system developed by UNCTAD's Investment and Enterprise Division, Business Facilitation Program and licensed under Creative Commons License