Invalid column name 'oldid'.
List of steps
(Total number of steps: 58)
Meet Investment Promotion Centre (IPC)
Obtain investment intent  (4)
Prepare master plan drawing profile  (1)
Obtain land location  (11)
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of documents  (2)
Obtain certified translation of documents  (2)
Obtain approval of master plan  (2)
Obtain approval of environment impact assessment (EIA) report  (6)
Obtain authenticated copies of documents  (1)
Declare investment project information online
Obtain investment registration certificate (IRC)  (2)
Obtain authenticated copies of IRC  (1)
Obtain Enterprise Registration Certificate (ERC)  (3)
Make seal and notify seal specimen  (2)
38
Make seal
Open bank account  (1)
Obtain approval of land lease and sign land lease contract  (3)
Obtain authenticated copies of documents  (1)
Obtain land use right certificate  (2)
Obtain certificate of fire prevention and fighting approval  (3)
Obtain authenticated copies of documents  (1)
Obtain approval of the conceptual plans of project  (3)
Obtain investigation on construction design  (3)
Obtain construction permit  (2)

Preview & Print

Properties
 
43
Sign the land lease contract
(last modified: 8/21/2017)

Timeframe ( ver detalles )

Espera hasta paso siguiente

5 mn  -  15 mn
10 days  -  20 days

Contact details

Entity in charge

Danang Department of Natural Resources and Environment (DONRE)

Floor 15th, Danang Administration Centre building, No. 24 Tran Phu street , Danang
Tel: +84 511 382 2410
Tel. 1: +84 511 386 3021
Email: tnmt@danang.gov.vn
Website: http://tnmt.danang.gov.vn

Unit in charge

Counter 8 - Reception and release division - Ground floor - Danang Administration Centre

Mon: 07:30-11:30, 13:30-17:30
Tue: 07:30-11:30, 13:30-17:30
Wed: 07:30-11:30, 13:30-17:30
Thu: 07:30-11:30, 13:30-17:30
Fri: 07:30-11:30, 13:30-17:30

Person in charge

Ms. Mai My My

Officer
Tel: +84 511 382 2410, +84 905 188 910
Email: mymm@danang.gov.vn

Expected results

Signed Land lease contract Signed Land lease contract
Minute on hand over land 01 - Minute on hand over land

Requirements

1. 01 - Libre deuda de patente
Passport or Vietnamese ID card of investor (original)
of the investor or of his/her legal representative

Time frame

Waiting time in queue: Max. 5mn
Attention at counter: Min. 5mn - Max. 10mn
Waiting time until next step: Min. 10 days - Max. 20 days

Legal justification

1. Law on land No.45/2013/QH13 of the National Assembly No.13
Law on land No.45/2013/QH13 of the National Assembly No.13
Article 56.d

Recourse: Danang Department of Natural Resources and Environment (DONRE)

Entity in charge

Danang Department of Natural Resources and Environment (DONRE)

Floor 15th, Danang Administration Centre building, No. 24 Tran Phu street , Danang
Tel: +84 511 382 2410
Tel. 1: +84 511 386 3021
Email: tnmt@danang.gov.vn
Website: http://tnmt.danang.gov.vn

Unit in charge

Counter 8 - Reception and release division - Ground floor - Danang Administration Centre

Mon: 07:30-11:30, 13:30-17:30
Tue: 07:30-11:30, 13:30-17:30
Wed: 07:30-11:30, 13:30-17:30
Thu: 07:30-11:30, 13:30-17:30
Fri: 07:30-11:30, 13:30-17:30

Person in charge

Mr. Pham Xuan Thu

Chief of office
Tel: +84 511 384 9272
Powered by eRegulations (c), a content management system developed by UNCTAD's Investment and Enterprise Division, Business Facilitation Program and licensed under Creative Commons License