List of steps
(Total number of steps: 58)
Meet Investment Promotion Centre (IPC)
Obtain investment intent  (4)
Prepare master plan drawing profile  (1)
Obtain land location  (11)
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of documents  (2)
Obtain certified translation of documents  (2)
Obtain approval of master plan  (2)
Obtain approval of environment impact assessment (EIA) report  (6)
Obtain authenticated copies of documents  (1)
Declare investment project information online
Obtain investment registration certificate (IRC)  (2)
Obtain authenticated copies of IRC  (1)
Obtain Enterprise Registration Certificate (ERC)  (3)
Make seal and notify seal specimen  (2)
38
Make seal
Open bank account  (1)
Obtain approval of land lease and sign land lease contract  (3)
Obtain authenticated copies of documents  (1)
Obtain land use right certificate  (2)
Obtain certificate of fire prevention and fighting approval  (3)
Obtain authenticated copies of documents  (1)
Obtain approval of the conceptual plans of project  (3)
Obtain investigation on construction design  (3)
Obtain construction permit  (2)

Preview & Print

Properties
 
9
Submit application for appraisal of land use needs and conditions to allocate land
(last modified: 8/21/2017)

Timeframe ( ver detalles )

Espera hasta paso siguiente

0 mn  -  15 mn
7 days  -  10 days

Contact details

Entity in charge

Danang Department of Natural Resources and Environment (DONRE)

Floor 15th, Danang Administration Centre building, No. 24 Tran Phu street , Danang
Tel: +84 511 382 2410
Tel. 1: +84 511 386 3021
Email: tnmt@danang.gov.vn
Website: http://tnmt.danang.gov.vn

Unit in charge

Counter 8 - Reception and release division - Ground floor - Danang Administration Centre

Mon: 07:30-11:30, 13:30-17:30
Tue: 07:30-11:30, 13:30-17:30
Wed: 07:30-11:30, 13:30-17:30
Thu: 07:30-11:30, 13:30-17:30
Fri: 07:30-11:30, 13:30-17:30

Person in charge

Ms. Mai My My

Officer
Tel: +84 511 382 2410, +84 905 188 910
Email: mymm@danang.gov.vn

Expected results

Receipt of application file 01 - Receipt of application file

Requirements

1. 01 - Libre deuda de patente
Written request for appraisal of land use needs
2. 01 - Libre deuda de patente
Report on land use need and project scale (Simple copy)
3. 01 - Libre deuda de patente
Investment intent approval (Simple copy)

Time frame

Waiting time in queue: Max. 5mn
Attention at counter: Max. 10mn
Waiting time until next step: Min. 7 days - Max. 10 days

Legal justification

1. Law on land No.45/2013/QH13 of the National Assembly No.13
Law on land No.45/2013/QH13 of the National Assembly No.13
Article 58.3
2. Decree 43/2014/ND-CP of  the Government specifying the enforcement of a number of provision of the Land Law 45/2013/QH13
Decree 43/2014/ND-CP of the Government specifying the enforcement of a number of provision of the Land Law 45/2013/QH13
Article 14
3. Circular 30/2014/TT-BTNMT of the Ministry of Environmental and Natural Resource, regulating on application of land lease and land allocation
Circular 30/2014/TT-BTNMT of the Ministry of Environmental and Natural Resource, regulating on application of land lease and land allocation
Article 3

Additional information

Investor shall prepare 7 sets of applications file, including 1 original set and 6 simple copy set

Recourse: Danang Department of Natural Resources and Environment (DONRE)

Entity in charge

Danang Department of Natural Resources and Environment (DONRE)

Floor 15th, Danang Administration Centre building, No. 24 Tran Phu street , Danang
Tel: +84 511 382 2410
Tel. 1: +84 511 386 3021
Email: tnmt@danang.gov.vn
Website: http://tnmt.danang.gov.vn

Unit in charge

Counter 8 - Reception and release division - Ground floor - Danang Administration Centre

Mon: 07:30-11:30, 13:30-17:30
Tue: 07:30-11:30, 13:30-17:30
Wed: 07:30-11:30, 13:30-17:30
Thu: 07:30-11:30, 13:30-17:30
Fri: 07:30-11:30, 13:30-17:30

Person in charge

Mr. Pham Xuan Thu

Chief of office
Tel: +84 511 384 9272