List of steps
(Total number of steps: 58)
Meet Investment Promotion Centre (IPC)
Obtain investment intent  (4)
Prepare master plan drawing profile  (1)
Obtain land location  (11)
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of documents  (2)
Obtain certified translation of documents  (2)
Obtain approval of master plan  (2)
Obtain approval of environment impact assessment (EIA) report  (6)
Obtain authenticated copies of documents  (1)
Declare investment project information online
Obtain investment registration certificate (IRC)  (2)
Obtain authenticated copies of IRC  (1)
Obtain Enterprise Registration Certificate (ERC)  (3)
Make seal and notify seal specimen  (2)
38
Make seal
Open bank account  (1)
Obtain approval of land lease and sign land lease contract  (3)
Obtain authenticated copies of documents  (1)
Obtain land use right certificate  (2)
Obtain certificate of fire prevention and fighting approval  (3)
Obtain authenticated copies of documents  (1)
Obtain approval of the conceptual plans of project  (3)
Obtain investigation on construction design  (3)
Obtain construction permit  (2)

Preview & Print

Properties
 
51
Prepare drawing profile
(last modified: 8/21/2017)

Costs

( ver detalles )

Timeframe ( ver detalles )

Espera hasta paso siguiente

Free of charge
0 mn  -  25 mn
3 days  -  10 days

Expected results

Conceptual design presentation x2 01 - Conceptual design presentation
Drawing of conceptual design x2 01 - Drawing of conceptual design
Geo-technical survey profile x2 01 - Geo-technical survey profile
Meeting minute of topographical survey x2 01 - Meeting minute of topographical survey
Certificate of business registration of the design consulting firm 01 - Certificate of business registration of the design consulting firm
License of designer 01 - License of designer
CD disk recording relevant drawing 01 - CD disk recording relevant drawing

Costs

Payment methods: cash, bank transfer
Investors can conduct the topographical survey and produce 1/500-scale construction plan themselves if they employ sufficient qualified architects, engineers and workers. Otherwise, they have to outsource the survey and the plan. And it will incur costs.

Time frame

Waiting time in queue: Max. 5mn
Attention at counter: Max. 20mn
Waiting time until next step: Min. 3 days - Max. 10 days

Legal justification

1. Law No. 30/2009/QH12  of National Assembly on urban planning
Law No. 30/2009/QH12 of National Assembly on urban planning
Article 10