List of steps
(Total number of steps: 58)
Meet Investment Promotion Centre (IPC)
Obtain investment intent  (4)
Prepare master plan drawing profile  (1)
Obtain land location  (11)
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of documents  (2)
Obtain certified translation of documents  (2)
Obtain approval of master plan  (2)
Obtain approval of environment impact assessment (EIA) report  (6)
Obtain authenticated copies of documents  (1)
Declare investment project information online
Obtain investment registration certificate (IRC)  (2)
Obtain authenticated copies of IRC  (1)
Obtain Enterprise Registration Certificate (ERC)  (3)
Make seal and notify seal specimen  (2)
38
Make seal
Open bank account  (1)
Obtain approval of land lease and sign land lease contract  (3)
Obtain authenticated copies of documents  (1)
Obtain land use right certificate  (2)
Obtain certificate of fire prevention and fighting approval  (3)
Obtain authenticated copies of documents  (1)
Obtain approval of the conceptual plans of project  (3)
Obtain investigation on construction design  (3)
Obtain construction permit  (2)

Preview & Print

Properties
 
54
Prepare drawing profile
(last modified: 8/21/2017)

Costs

( ver detalles )

Timeframe ( ver detalles )

Espera hasta paso siguiente

Free of charge
0 mn  -  15 mn
3 days  -  10 days

Expected results

Drawing of each project on a plot ratio of 1/100 - 1/500 x2 01 - Drawing of each project on a plot ratio of 1/100 - 1/500
Drawings façade and main section of each work ratio 1/50 - 1/200 x2 01 - Drawings façade and main section of each work ratio 1/50 - 1/200
Foundation drawings of each work ratio 1/100 - 1/200 and foundation section of each work ratio 1/50 x2 01 - Foundation drawings of each work ratio 1/100 - 1/200 and foundation section of each work ratio 1/50
Diagram of rainwater drainage, waste water treatment, water supply, power, ratio 1/50 - 1/200 x2 01 - Diagram of rainwater drainage, waste water treatment, water supply, power, ratio 1/50 - 1/200
CD disk recording relevant drawing 01 - CD disk recording relevant drawing
General report as regulated at article 20.1.a-b of Decree 15/2013/ND-CP 01 - General report as regulated at article 20.1.a-b of Decree 15/2013/ND-CP

Costs

Payment methods: cash
The cost is determined based on project's scale ( in terms of hectares or square metters) and agreements of parties in the service contract.

Time frame

Waiting time in queue: Max. 5mn
Attention at counter: Max. 10mn
Waiting time until next step: Min. 3 days - Max. 10 days

Legal justification

1. Circular 16/2013/TT-BXD of Ministry of Construction amending Circular 06/2013/TT-BXD
Circular 16/2013/TT-BXD of Ministry of Construction amending Circular 06/2013/TT-BXD
Article 1
2. Circular 01/2013/TT-BXD of Ministry of Construction, guiding, identifying and managing fees for construction planning and urban planning
Circular 01/2013/TT-BXD of Ministry of Construction, guiding, identifying and managing fees for construction planning and urban planning
articles 4, 5, 6, 7