List of steps
(Total number of steps: 40)
Meet Danang Industrial and Export Processing Zones Authority (DIEPZA)
Sign MOU on land lease  (1)
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of documents  (2)
Obtain certified translation of documents  (2)
Obtain authenticated copies of documents  (1)
Obtain approval of environment impact assessment (EIA) report  (6)
Declare investment project information online
Obtain investment registration certificate (IRC)  (2)
Obtain authenticated copies of IRC  (1)
Obtain Enterprise Registration Certificate (ERC)  (3)
Make seal and notify seal specimen  (2)
21
Make seal
Open bank account  (1)
Obtain land lease contract and receive land plot on site  (2)
Obtain authenticated copies of signed land lease contract  (1)
Obtain construction planning certificate  (2)
Prepare construction drawing profile  (1)
Obtain authenticated copies of documents  (1)
Obtain land use right certificate  (2)
Obtain Infrastructure connection agreement  (2)
Obtain certificate of fire prevention and fighting approval  (3)
Obtain authenticated copies of documents  (1)
Obtain Master plan agreement and architectural construction solution  (2)

Preview & Print

Properties
 
36
Submit application for fire prevention and fighting approval
(last modified: 1/21/2017)

Costs

( ver detalles )

Timeframe ( ver detalles )

Espera hasta paso siguiente

Free of charge
0 mn  -  20 mn
5 days  -  15 days

Contact details

Entity in charge

Danang Police on Fire Prevention and fighting

183, Phan Dang Luu Str., Hai Chau Dist. , Danang
Tel: +84 511 3644 538
Tel. 1: +84 511 3644 524
Website: http://pccc.danang.gov.vn

Unit in charge

Reception and release unit

Mon: 07:30-11:00, 14:00-17:00
Tue: 07:30-11:00, 14:00-17:00
Wed: 07:30-11:00, 14:00-17:00
Thu: 07:30-11:00, 14:00-17:00
Fri: 07:30-11:00, 14:00-17:00

Person in charge

Nguyen Thi Xuan Thuy/Tran Bao Cuong/Pham Dinh Hai/Pham Huu Tuan

Officer
Tel: +84 511 3644 538

Expected results

Receipt of fire prevention and fighting appraisal application Receipt of fire prevention and fighting appraisal application

Requirements

Representatives
A. For all cases:
1. Application for approval of fire prevention and fighting
Application for approval of fire prevention and fighting (original)
2. Documents showing the ability of the designing firm
Documents showing the ability of the designing firm
3. 01 - Libre deuda de patente
Authenticated copy of IRC
if any
4. 01 - Libre deuda de patente
Authenticated copies of land use right, house and land-attached asset ownership certificate
B. For specific application files
I. For planning projects application file, supplement:
1. 01 - Libre deuda de patente
Drawings for fight prevention and fighting (original)
with ratio 1:500 and following Clause 1, 2, 3, 4 Article 12 of Decree 79/2014/ND-CP
2. 01 - Libre deuda de patente
Cost estimation of total investment capital of project, building works
II. For conceptual design application file, supplement:
1. 01 - Libre deuda de patente
Drawings for fight prevention and fighting (original)
showing conceptual design and following the Clause 1, 2, 3, 4, 5 and 6 Article 13 of Decree 79/2014/ND-CP
2. 01 - Libre deuda de patente
Authenticated copy of IRC
3. 01 - Libre deuda de patente
Cost estimation of total investment capital of project, building works
III. For approval of construction location application file, supplement:
1. 01 - Libre deuda de patente
Drawings for fight prevention and fighting (original)
indicate clearly the location situation: wind direction, height of construction work, level of fire resistance, the information about the topography of the land, climate, hydrology, distance from the proposed construction works to other surrounding works.
2. 01 - Libre deuda de patente
Authenticated copies of land use right, house and land-attached asset ownership certificate
or any documents that certify the land use right or construction work
IV. For construction drawings application file, supplement:
1. 01 - Libre deuda de patente
Drawings for fight prevention and fighting (original)
following Clause 1, 2, 3, 4, 5 and 6 Article 13 of Decree No. 79/2014/ND-CP
2. 01 - Libre deuda de patente
Authenticated copies of approval of master plan
3. 01 - Libre deuda de patente
Cost estimation of total investment capital of project, building works
V. For approval of vehicles, supplement:
1. 01 - Libre deuda de patente
Authenticated copy of IRC
2. 01 - Libre deuda de patente
Drawings for fight prevention and fighting (original)
expressing solutions to ensure safety for fire prevention and fighting against nature activities and characteristics of dangerous fire and explosion of the vehicle; conditions to prevent fire spread fire protection, escape, rescue people in case of fire; measures to ensure the safety of fire prevention and fighting for power systems, fuel systems and engines; fire alarm system, fire fighting and other fire fighting vehicles; systems, detection equipment and troubleshooting of gas leaks, hazardous liquids and explosives.
3. 01 - Libre deuda de patente
Cost estimation of total investment capital of vehicles
prepared by investors
VI. In case of authorization, supplement:
1. 01 - Libre deuda de patente
Power of attorney (an authentic copy)
issued by investor for the authorized person in case investor is unable to come to submit application file

Costs

The fees for approval of fire prevention and fighting is calculated based on article 4 of the Circular 150/2014/TT-BTC.
The article 5 of the Circular 150/2014/TT-BTC regulates when the payment should be made for each case of fire prevention and fighting approval

Time frame

a) For planning projects: Within 10 working days;
b) For basic designs: Within 10 working days for projects of Group A; within 5 working days for projects of Group B and Group C;
c) For construction location approval: Within 05 working days;
d) For construction drawing: Within 15 working days for projects and constructions of Group A; within 10 working days for projects and constructions of Group B and Group C;
The classification of projects and constructions to Group A, B, C shall be carried out under the Government’s provisions on construction investment project management in Annex 1, Decree 12/2009/NĐ-CP dated 10/02/2009.
Waiting time in queue: Max. 5mn
Attention at counter: Max. 15mn
Waiting time until next step: Min. 5 days - Max. 15 days

Legal justification

1. Law on fire prevention and fighting of National Assembly
Law on fire prevention and fighting of National Assembly
Article 15
2. Law no. 40/2013/QH13 of National Assembly, amending and supplementing few articles of the Law on fire prevention and fighting
Law no. 40/2013/QH13 of National Assembly, amending and supplementing few articles of the Law on fire prevention and fighting
Article 1
3. Decree 79/2014/NĐ-CP of the Government guiding on implementation of the Law on fire prevention and fighting
Decree 79/2014/NĐ-CP of the Government guiding on implementation of the Law on fire prevention and fighting
articles 13, 15
4. Circular 150/2014/TT-BTC of Ministry of Finance regulating collection and use of fees of approval of fire prevention and fighting
Circular 150/2014/TT-BTC of Ministry of Finance regulating collection and use of fees of approval of fire prevention and fighting
articles 4, 5
5. Circular 66/2014/TT-BCA regulates implementation of few articles of Decree 79/2014/NĐ-CP which regulates implementation of the Law of fire prevention and frighting
Circular 66/2014/TT-BCA regulates implementation of few articles of Decree 79/2014/NĐ-CP which regulates implementation of the Law of fire prevention and frighting
Chapter 2 ,  Article 7

Recourse: Danang Police on Fire Prevention and fighting

Entity in charge

Danang Police on Fire Prevention and fighting

183, Phan Dang Luu Str., Hai Chau Dist. , Danang
Tel: +84 511 3644 538
Tel. 1: +84 511 3644 524
Website: http://pccc.danang.gov.vn

Unit in charge

Department on guidance of fire prevention

Mon: 08:00-11:00, 14:00-16:30
Tue: 08:00-11:00, 14:00-16:30
Wed: 08:00-11:00, 14:00-16:30
Thu: 08:00-11:00, 14:00-16:30
Fri: 08:00-11:00, 14:00-16:30

Person in charge

Mr. Nguyen Huy Phong

Head of department
Tel: +84 511 387 9778
Email: nguyenhuyphongpc66@gmail.com