List of steps
(Total number of steps: 40)
Meet Danang Industrial and Export Processing Zones Authority (DIEPZA)
Sign MOU on land lease  (1)
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of documents  (2)
Obtain certified translation of documents  (2)
Obtain authenticated copies of documents  (1)
Obtain approval of environment impact assessment (EIA) report  (6)
Declare investment project information online
Obtain investment registration certificate (IRC)  (2)
Obtain authenticated copies of IRC  (1)
Obtain Enterprise Registration Certificate (ERC)  (3)
Make seal and notify seal specimen  (2)
21
Make seal
Open bank account  (1)
Obtain land lease contract and receive land plot on site  (2)
Obtain authenticated copies of signed land lease contract  (1)
Obtain construction planning certificate  (2)
Prepare construction drawing profile  (1)
Obtain authenticated copies of documents  (1)
Obtain land use right certificate  (2)
Obtain Infrastructure connection agreement  (2)
Obtain certificate of fire prevention and fighting approval  (3)
Obtain authenticated copies of documents  (1)
Obtain Master plan agreement and architectural construction solution  (2)

Preview & Print

Properties
 
33
Submit application for infrastructure connection agreement
(last modified: 1/21/2017)

Espera hasta paso siguiente

3 days  -  5 days

Contact details

Entity in charge

Any Infrastructure Development Company (IDC)


List of infrastructure development companies List of infrastructure development companies

Requirements

Investor needs to prepare 06 original sets of application files, each one includes the followings:
1. Application for infrastructure connection agreement
Application for infrastructure connection agreement (original)
2. 01 - Libre deuda de patente
Authenticated copies of decision on approval of EIA report
3. 01 - Libre deuda de patente
Drawings of technical infrastructure connection (original)

Time frame

Waiting time until next step: Min. 3 days - Max. 5 days

Legal justification

1. Decree 29/2008/NĐ-CP of the Government regulating on industrial parks, economic zones and export processing zones
Decree 29/2008/NĐ-CP of the Government regulating on industrial parks, economic zones and export processing zones
Chapter V ,  Article 38

Additional information

* Investor should prepare 6 original sets of application files and will get back 2 sets after approval
* The Infrastructure Development Company (IDC) will check the application file. If it is proper application file, within 5 days IDC will issue an Infrastructure Connection Agreement and send to investor to sign and seal.