List of steps
(Total number of steps: 40)
Meet Danang Industrial and Export Processing Zones Authority (DIEPZA)
Sign MOU on land lease  (1)
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of documents  (2)
Obtain certified translation of documents  (2)
Obtain authenticated copies of documents  (1)
Obtain approval of environment impact assessment (EIA) report  (6)
Declare investment project information online
Obtain investment registration certificate (IRC)  (2)
Obtain authenticated copies of IRC  (1)
Obtain Enterprise Registration Certificate (ERC)  (3)
Make seal and notify seal specimen  (2)
21
Make seal
Open bank account  (1)
Obtain land lease contract and receive land plot on site  (2)
Obtain authenticated copies of signed land lease contract  (1)
Obtain construction planning certificate  (2)
Prepare construction drawing profile  (1)
Obtain authenticated copies of documents  (1)
Obtain land use right certificate  (2)
Obtain Infrastructure connection agreement  (2)
Obtain certificate of fire prevention and fighting approval  (3)
Obtain authenticated copies of documents  (1)
Obtain Master plan agreement and architectural construction solution  (2)

Preview & Print

Properties
 
34
Collect the infrastructure connection agreement
(last modified: 1/21/2017)

Contact details

Entity in charge

Any Infrastructure Development Company (IDC)


List of infrastructure development companies List of infrastructure development companies

Expected results

Infrastructure connection agreement 01 - Infrastructure connection agreement

Additional information

The IDC will send the Infrastructure connection agreement to investor, thus he/she doesn't need to come to IDC to collect it.