Meet Danang Industrial and Export Processing Zones Authority (DIEPZA)
Sign MOU on land lease  (1)
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of documents  (2)
Obtain certified translation of documents  (2)
Obtain authenticated copies of documents  (1)
Obtain approval of environment impact assessment (EIA) report  (6)
Declare investment project information online
Obtain investment registration certificate (IRC)  (2)
Obtain authenticated copies of IRC  (1)
Obtain Enterprise Registration Certificate (ERC)  (3)
Make seal and notify seal specimen  (2)
21
Make seal
Open bank account  (1)
Obtain land lease contract and receive land plot on site  (2)
Obtain authenticated copies of signed land lease contract  (1)
Obtain construction planning certificate  (2)
Prepare construction drawing profile  (1)
Obtain authenticated copies of documents  (1)
Obtain land use right certificate  (2)
Obtain Infrastructure connection agreement  (2)
Obtain certificate of fire prevention and fighting approval  (3)
Obtain authenticated copies of documents  (1)
Obtain Master plan agreement and architectural construction solution  (2)

Preview & Print

Properties
 
13
Submit finalized EIA report
(last modified: 1/21/2017)

Timeframe ( ver detalles )

Espera hasta paso siguiente

0 mn  -  15 mn
10 days  -  15 days

Contact details

Entity in charge

Environmental Protection Agency-Danang Department of Natural Resources and Environment

24 Ho Nguyen Trung Street, Hai Chau District , Danang
Tel: +84 511 374 0449
Tel. 1: +84 511 374 0449
Email: ccbvmt@danang.gov.vn
Website: www.ccbvmt.danang.gov.vn

Unit in charge

Assessment and Licence Division

Mon: 07:30-11:30, 13:30-17:30
Tue: 07:30-11:30, 13:30-17:30
Wed: 07:30-11:30, 13:30-17:30
Thu: 07:30-11:30, 13:30-17:30
Fri: 07:30-11:30, 13:30-17:30

Person in charge

Mr. Nguyen Hoang Huy/Ms. Nguyen Hoang Dung

Officer
Tel: +84 511 374 0448

Expected results

Receipt of finalized EIA report application 01 - Receipt of finalized EIA report application

Requirements

1. 01 - Libre deuda de patente
Amended EIA report (4 original )
2. 01 - Libre deuda de patente
Written explanation on EIA report content of amendment (original)
3. 01 - Libre deuda de patente
CD room containing finalized EIA report (original)

Time frame

Waiting time in queue: Max. 5mn
Attention at counter: Max. 10mn
Waiting time until next step: Min. 10 days - Max. 15 days

Legal justification

1. Law  No. 52/2005/QH11 of National Assembly on Environmental Protection
Law No. 52/2005/QH11 of National Assembly on Environmental Protection
Article 21
2. Decree 29/2011/NĐ-CP of the Government providing strategic environmental assessment, environmental impact assessment and environmental protection commitment (Eng)
Decree 29/2011/NĐ-CP of the Government providing strategic environmental assessment, environmental impact assessment and environmental protection commitment (Eng)
articles 13, 14, 15, 16, 17
3. Circular 26/2011/TT-BTNMT of Ministry of Natural Resources and Environment specifying some articles of Decree 29/2011/ND-CP on strategic environment assessments, environment impact assessments, environment protection plans
Circular 26/2011/TT-BTNMT of Ministry of Natural Resources and Environment specifying some articles of Decree 29/2011/ND-CP on strategic environment assessments, environment impact assessments, environment protection plans
articles 14, 15

Additional information

Amended Environment Impact Assessment Report will be made by investors based on comments of the meeting's Chairman, which are recorded in the "Official Minutes of Appraisal Council". After completing, investors submit finalized dossiers again to One Door Unit -Environmental Protection Agency-Danang Department Of Natural Resources And Environment for approval.

Recourse: Environmental Protection Agency-Danang Department of Natural Resources and Environment

Entity in charge

Environmental Protection Agency-Danang Department of Natural Resources and Environment

24 Ho Nguyen Trung Street, Hai Chau District , Danang
Tel: +84 511 374 0449
Tel. 1: +84 511 374 0449
Email: ccbvmt@danang.gov.vn
Website: www.ccbvmt.danang.gov.vn

Unit in charge

Assessment and Licence Division

Mon: 07:30-11:30, 13:30-17:30
Tue: 07:30-11:30, 13:30-17:30
Wed: 07:30-11:30, 13:30-17:30
Thu: 07:30-11:30, 13:30-17:30
Fri: 07:30-11:30, 13:30-17:30

Person in charge

Ms. Doan Thi Kim Anh

Deputy of Division
Tel: +84 511 374 0448