List of steps
(Total number of steps: 46)
Meet Danang Hi-Tech Park (DHTP)
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of documents  (2)
Obtain certified translation of documents  (2)
Obtain authenticated copies of passports and/or Vietnamese ID cards  (1)
Obtain written approval of investment and introduction of project location  (4)
Obtain approval of environment impact assessment (EIA) report  (6)
Declare investment project information online
Obtain investment registration certificate (IRC)  (2)
Obtain authenticated copies of IRC  (1)
Obtain Enterprise Registration Certificate (ERC)  (3)
Make seal and notify seal specimen  (2)
24
Make seal
Open bank account  (1)
Obtain approval of land allocation or land lease and sign land lease contract  (3)
Obtain authenticated copy of documents  (1)
Obtain certificate of construction planning  (2)
Prepare construction drawing profile  (1)
Obtain approval of the detailed construction planning task  (2)
Obtain approval of the detailed construction plan and architectural plan of project  (2)
Obtain land use right certificate  (2)
Obtain certificate of fire prevention and fighting approval  (3)
Obtain approval of the conceptual plans of projects  (2)
Obtain construction permit  (2)

Preview & Print

Properties
 
31
Submit application for certificate of construction planning
(last modified: 8/21/2017)

Timeframe ( ver detalles )

Espera hasta paso siguiente

0 mn  -  15 mn
0 days  -  7 days

Contact details

Entity in charge

Danang Hi-Tech Park Management Board

31st Floor, Danang Administration Centre building, No. 24 Tran Phu street , Da Nang
Tel: +84 511 3566 704
Tel. 1: +84 511 3566 705
Email: websitedhtp@danang.gov.vn
Website: http://dhtp.gov.vn

Unit in charge

Counter 11 - Reception and release division - Ground floor - Danang Administration Centre

Mon: 07:30-11:30, 13:30-17:30
Tue: 07:30-11:30, 13:30-17:30
Wed: 07:30-11:30, 13:30-17:30
Thu: 07:30-11:30, 13:30-17:30
Fri: 07:30-11:30, 13:30-17:30

Person in charge

Ms. Truong Thi Bich Hong / Ms. Nguyen Thi Cat Tuong

Officer
Tel: +84 511 3566 704

Expected results

Receipt of application file 01 - Receipt of application file

Requirements

Investors submit 3 sets of application file, each set contains the followings:
1. Request for  issuing Certificate on construction planning
Request for issuing Certificate on construction planning (original)
2. 01 - Libre deuda de patente
Approval of land allocation or land lease (Simple copy)
3. 01 - Libre deuda de patente
Minutes of transferring boundary mark (Simple copy)
4. 01 - Libre deuda de patente
Drawing of the land location (Simple copy)

Time frame

Waiting time in queue: Max. 5mn
Attention at counter: Max. 10mn
Waiting time until next step: Max. 7 days

Legal justification

1. Law No. 16/2003/QH11 of National Assembly on Construction
Law No. 16/2003/QH11 of National Assembly on Construction
Article 33
2. Decision 1979/QĐ-TTg of Prime Minister on establishment and operation of Danang Hi-Tech Park
Decision 1979/QĐ-TTg of Prime Minister on establishment and operation of Danang Hi-Tech Park
Article 9.4.c

Recourse: Danang Hi-Tech Park Management Board

Entity in charge

Danang Hi-Tech Park Management Board

31st Floor, Danang Administration Centre building, No. 24 Tran Phu street , Da Nang
Tel: +84 511 3566 704
Tel. 1: +84 511 3566 705
Email: websitedhtp@danang.gov.vn
Website: http://dhtp.gov.vn

Unit in charge

Counter 11 - Reception and release division - Ground floor - Danang Administration Centre

Mon: 07:30-11:30, 13:30-17:30
Tue: 07:30-11:30, 13:30-17:30
Wed: 07:30-11:30, 13:30-17:30
Thu: 07:30-11:30, 13:30-17:30
Fri: 07:30-11:30, 13:30-17:30

Person in charge

Mr. Tran Quoc Cuong

Head of administration dept
Tel: +84 511 3566 704