List of steps
(Total number of steps: 46)
Meet Danang Hi-Tech Park (DHTP)
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of documents  (2)
Obtain certified translation of documents  (2)
Obtain authenticated copies of passports and/or Vietnamese ID cards  (1)
Obtain written approval of investment and introduction of project location  (4)
Obtain approval of environment impact assessment (EIA) report  (6)
Declare investment project information online
Obtain investment registration certificate (IRC)  (2)
Obtain authenticated copies of IRC  (1)
Obtain Enterprise Registration Certificate (ERC)  (3)
Make seal and notify seal specimen  (2)
24
Make seal
Open bank account  (1)
Obtain approval of land allocation or land lease and sign land lease contract  (3)
Obtain authenticated copy of documents  (1)
Obtain certificate of construction planning  (2)
Prepare construction drawing profile  (1)
Obtain approval of the detailed construction planning task  (2)
Obtain approval of the detailed construction plan and architectural plan of project  (2)
Obtain land use right certificate  (2)
Obtain certificate of fire prevention and fighting approval  (3)
Obtain approval of the conceptual plans of projects  (2)
Obtain construction permit  (2)

Preview & Print

Properties
 
40
Prepare drawing profile
(last modified: 8/21/2017)

Costs

( ver detalles )

Timeframe ( ver detalles )

Espera hasta paso siguiente

Free of charge
0 mn  -  0 mn
10 days  -  15 days

Expected results

Drawings for fight prevention and fighting x2 01 - Drawings for fight prevention and fighting
Cost estimation of total investment capital of project, building works x3 01 - Cost estimation of total investment capital of project, building works
License of the designer License of the designer
Documents showing the ability of the designing firm Documents showing the ability of the designing firm

Costs

Cost will be based on project scale and complexity

Time frame

Attention at counter: Max. 30mn
Waiting time until next step: Min. 10 days - Max. 15 days

Additional information

Investor can choose any designing firm in Danang. Please see the Contact details for references.